Contemporary Whole Home Renovation
Whole Home

Contemporary Whole Home Renovation

Complete home transformation including kitchen, bathrooms, flooring, and open concept living areas in Apopka, FL.

Location

Apopka, FL

Completed

November 2023

Investment

$175,000

Size

2,400 sq ft

Project Specifications

Detailed specifications, materials, and features used in this whole home project.

Kitchen
Cabinets:Flat Panel, High Gloss White
Countertops:Quartz - Pure White
Backsplash:Large Format Porcelain
Appliances:Stainless Steel Package
Flooring
Main Areas:Luxury Vinyl Plank - Oak
Bathrooms:Large Format Porcelain Tile
Bedrooms:Luxury Vinyl Plank - Oak
Transition Strips:Matching Wood Grain
Bathrooms
Master Tub:Freestanding Acrylic
Showers:Frameless Glass Enclosures
Vanities:Floating Style
Fixtures:Brushed Nickel Finish
Interior
Paint:Sherwin Williams - Agreeable Gray
Trim:White MDF Baseboards
Doors:Contemporary Flat Panel
Hardware:Brushed Nickel
Key Features
Open concept living area
Modern kitchen with large island
Luxury master bathroom suite
Contemporary interior design
Energy-efficient LED lighting
Updated electrical and plumbing
New HVAC system with smart thermostat
Luxury vinyl plank flooring
Project Team

Project Manager

Michael Chen

Lead Craftsman

David Wilson

Designer

Amanda Foster

Project Details

Duration

20 weeks

Investment

$175,000

Square Footage

2,400 sq ft

Completed

November 2023

Challenges & Solutions

Coordinating multiple trades for whole home renovation

Detailed scheduling and communication between trades

Living in home during construction phases

Phased construction to maintain livable spaces

Matching new work with existing architectural elements

Careful selection of materials to complement existing features

Project Timeline

Follow the step-by-step process of this whole home project from start to completion.

Planning & Design

Comprehensive design and material selection

2 weeks
Whole home assessment
Design development
Material selection
Permit applications

Demolition

Selective demolition and preparation

1 week
Remove interior walls for open concept
Demo existing kitchen and bathrooms
Remove old flooring
Prepare for new systems

Structural Work

Structural modifications and systems

2 weeks
Install structural beam for open concept
Update electrical throughout
Upgrade plumbing systems
Install new HVAC system

Framing & Drywall

Interior framing and drywall installation

3 weeks
Frame new interior walls
Install insulation
Hang and finish drywall
Texture and prime walls

Kitchen Installation

Complete kitchen renovation

3 weeks
Install kitchen cabinets
Template and install countertops
Install backsplash tile
Install and connect appliances

Bathroom Renovations

All bathroom renovations

4 weeks
Install bathroom tile work
Install vanities and countertops
Install all bathroom fixtures
Install shower enclosures

Flooring & Paint

Flooring installation and interior painting

3 weeks
Install flooring throughout
Paint all interior surfaces
Install baseboards and trim
Install interior doors

Final Details

Finishing touches and cleanup

2 weeks
Install light fixtures
Install switch plates and outlets
Final touch-up painting
Deep cleaning and final walkthrough

Client Testimonial

Hear directly from the homeowner about their experience with this whole home project.

"Our entire home renovation was managed flawlessly from start to finish. Every room flows beautifully together, and the quality of workmanship is evident in every detail. It truly feels like we have a brand new home."
C

Carlos & Maria Rodriguez

Whole Home Project - Apopka, FL